skip to main |
skip to sidebar
Huizhou Pumped Storage Power Plant
7:05 AM
Posted by Energetic
The Huizhou Pumped Storage Power Plant is a pumped storage hydroelectric power station near Huizhou in Guangdong province, China. It contains 8 pump-generators that are all expected to be commercially online in 2011, totaling a 2,400 MW installed capacity. Initial units went online between 2007 and 2008.
The Huizhou Pumped Storage Power Plant is supplied with water by an upper reservoir which is created by two dams. The main dam is a 56 m (184 ft) tall and 156 m (512 ft) long roller compacted concrete (RCC) dam. The second, auxiliary, dam is 14 m (46 ft) high and 133 m (436 ft) long. Once water from the upper reservoir is transferred through the power station, which is located 420 m (1,380 ft) underground, and electricity produced, it discharges to a lower reservoir. This lower reservoir is created by a single 61 m (200 ft) tall 420 m (1,380 ft) tall RCC dam. The water can then be pumped by the generators back into the upper reservoir for reuse.| Huizhou Pumped-storage Power Station | |
|---|---|
| Country | |
| Locale | Huizhou, Guangdong |
| Status | Partially operational |
| Commission date | 2007 |
| Pumped-storage station information | |
| Pump-generators | 8 |
| Power generation information | |
| Maximum capacity | 2,400 MW |
| Annual generation | 4,200 GWh |
Guangdong Pumped Storage Plant
10:47 AM
Posted by Energetic
The Guangdong or Guangzhou Pumped Storage Power Plant is a pumped-storage hydroelectric power station near Guangzhou, Guangdong Proavince, China. Power is generated by utilizing eight turbines, each with a 300 MW capacity, totalling the installed capacity to 2,400 MW. The generated power is sold to China Light and Power customers in Hong Kong. The power station was constructed in two stages, the first four turbines were completed in 1994 and the second four in 2000.
The Guangdong Pumped Storage Power Plant is composed mainly of a lower and upper reservoir and and an underground power station. Water for the system is derived from the Liuxihe River. The lower reservoir has a capacity of 23,400,000 cubic metres (18,971 acre·ft) and is created by a 43.5 metres (143 ft) tall and 153.12 metres (502 ft) long gravity dam composed of roller-compacted concrete. Water from this reservoir is pumped into the upper reservoir which is created by a 68 metres (223 ft) tall and 318.52 metres (1,045 ft) long concrete face rock-fill embankment dam and has a capacity of 23,400,000 cubic metres (18,971 acre·ft) . Water from the upper reservoir can then be re-released down two penstocks towards the power station. The same reversible pumps that moved the water up can now generate electricity. Just before reaching the power station, the two penstocks each split off into four separate branch pipes, each feeding one of the eight reversible 300 MW turbine generators with water. Once power generation is complete, the generators can reverse, pump the water back up to the upper reservoir and resume the process over again.
The Guangdong Pumped Storage Power Plant is composed mainly of a lower and upper reservoir and and an underground power station. Water for the system is derived from the Liuxihe River. The lower reservoir has a capacity of 23,400,000 cubic metres (18,971 acre·ft) and is created by a 43.5 metres (143 ft) tall and 153.12 metres (502 ft) long gravity dam composed of roller-compacted concrete. Water from this reservoir is pumped into the upper reservoir which is created by a 68 metres (223 ft) tall and 318.52 metres (1,045 ft) long concrete face rock-fill embankment dam and has a capacity of 23,400,000 cubic metres (18,971 acre·ft) . Water from the upper reservoir can then be re-released down two penstocks towards the power station. The same reversible pumps that moved the water up can now generate electricity. Just before reaching the power station, the two penstocks each split off into four separate branch pipes, each feeding one of the eight reversible 300 MW turbine generators with water. Once power generation is complete, the generators can reverse, pump the water back up to the upper reservoir and resume the process over again.
| Guangdong Pumped Storage Power Station | |
|---|---|
| Country | |
| Locale | Guangdong |
| Status | Operational |
| Construction began | Stage I: 1989 Stage II: 1994 |
| Commission date | Stage I: 1994 Stage II: 2000 |
| Reservoir information | |
| Upper reservoir | Guangdong Upper |
| Reservoir capacity | 24,080,000 m3 (19,522 acre·ft) |
| Catchment area | 5.2 km2 (2 sq mi) |
| Surface area | 1.2 km2 (0 sq mi) |
| Lower reservoir | Guangdong Lower |
| Reservoir capacity | 23,400,000 m3 (18,971 acre·ft) |
| Catchment area | 13.2 km2 (5 sq mi) |
| Surface area | 1.6 km2 (1 sq mi) |
| Pumped-storage station information | |
| Pump-generators | 8 × 300MW |
| Hydraulic head | 535 m (1,755 ft) (max. gross) |
| Upper reservoir spillways | Service, controlled side channel chute |
| Lower reservoir spillways | Service, crest |
| Lower reservoir spillway discharge | 523 m3/s (18,470 cu ft/s) |
| Power generation information | |
| Installed capacity | 2,400 MW |
Kannagawa Hydroelectric Power Plant
11:48 AM
Posted by Energetic

The Kannagawa Hydroelectric Power Plant is an pumped-storage hydroelectric power plant near Minamiaiki in Nagano Prefecture and Gunma Prefecture, Japan. The power plant utilizes the Minamiaiki River along with an upper and lower reservoir created by two dams, the upper Minamiaiki Dam and the lower Ueno Dam. The power station in between the two dams will contain six 470 MW pump-generators for a total installed capacity of 2,820 MW. Only Unit 1 has commenced commercial operation and did so in 2005. When completed, the plant will have the largest pumped-storage power capacity in the world.
The Kannagawa Hydroelectric Power Plant is 1,600 ft (490 m) underground and measures 708 ft (216 m) long, 108 ft (33 m) wide, and 169 ft (52 m) high. It will contain 6 x 470 MW pump generators for a total capacity of 2,820 MW. Water from the upper Minamiaiki Reservoir is transferred through the power house and after producing electricity, it is brought to the lower Ueno Reservoir. The pump-generators can then pump water from the lower reservoir back up to the upper reservoir for re-use in hydroelectric power production. The water tunnel connecting the two reservoirs is 3.8 mi (6.1 km) long. The power station also has an effective hydraulic head of 653 m (2,142 ft) and maximum discharge of 510 m3/s (18,000 cu ft/s). Unit 1 commenced commercial operation in 2005 and Unit 2 is expected for 2012. The other four units are expected to be operational by 2020 or later.
The Kannagawa Hydroelectric Power Plant is 1,600 ft (490 m) underground and measures 708 ft (216 m) long, 108 ft (33 m) wide, and 169 ft (52 m) high. It will contain 6 x 470 MW pump generators for a total capacity of 2,820 MW. Water from the upper Minamiaiki Reservoir is transferred through the power house and after producing electricity, it is brought to the lower Ueno Reservoir. The pump-generators can then pump water from the lower reservoir back up to the upper reservoir for re-use in hydroelectric power production. The water tunnel connecting the two reservoirs is 3.8 mi (6.1 km) long. The power station also has an effective hydraulic head of 653 m (2,142 ft) and maximum discharge of 510 m3/s (18,000 cu ft/s). Unit 1 commenced commercial operation in 2005 and Unit 2 is expected for 2012. The other four units are expected to be operational by 2020 or later.
| Kannagawa Hydropower Plant | |
|---|---|
| Country | |
| Locale | Nagano Prefecture and Gunma Prefecture |
| Status | In partial operation |
| Commission date | 2005 (Unit 1) |
| Owner(s) | Tokyo Electric Power Company |
| Power station information | |
| Primary fuel | Hydroelectric |
| Generation units | 6 x 470 MW |
| Power generation information | |
| Installed capacity | 2,820 MW |
Mesen - Mezenskaya Tidal Power Plant
6:45 AM
Posted by Energetic
Mesen Tidal Power Plant is a tidal power plant in Bay Mezenski White Sea , Arkhangelsk region. It is planned that the station will have a capacity of 8 GW and its annual output of electricity will amount to 38.9 billion kWh. Where to stay in TEC Mezen Bay selected because of the large high tides, which here reaches 10 m.
Project to build Mezenskaya Tidal Power Plant began in the Soviet Union, however, due to the collapse of the country and shortage of funds the project frozen. Work on it has resumed after the reorganization of RAO UES.
Development leads JSC Malaya Mesen TEC, a subsidiary of RusHydro. The project is at feasibility stage of development investments (stage "Rationale for the alignment).
In late 2008, the decision of the parent company, the work had been suspended due to reduction of investment costs.
In 2006, the project "Small Mesen PES. Within its framework has been developed prototype floating block on which the orthogonal hydroelectric RSA-5 (the rotation axis is perpendicular to the flow of the turbine). Installed capacity of 1.5 MW unit, the diameter of the impeller is 5 m. The block was made to "ON" Sevmash ", and was then towed to the Barents Sea and is set for Kislogubskaya PES . At present (2009) maintained its full-scale tests.
Of a set of blocks of similar design is planned to create a large DOS (including Mezenskaya).
Electricity is expected to send in Western Europe by the ECO "East-West".
In the case of construction of the station annual fuel savings is estimated at 12.6 million tons of standard fuel , which will prevent the emission into the atmosphere of about 19.45 million tons of carbon dioxide.
Project to build Mezenskaya Tidal Power Plant began in the Soviet Union, however, due to the collapse of the country and shortage of funds the project frozen. Work on it has resumed after the reorganization of RAO UES.
Development leads JSC Malaya Mesen TEC, a subsidiary of RusHydro. The project is at feasibility stage of development investments (stage "Rationale for the alignment).
In late 2008, the decision of the parent company, the work had been suspended due to reduction of investment costs.
In 2006, the project "Small Mesen PES. Within its framework has been developed prototype floating block on which the orthogonal hydroelectric RSA-5 (the rotation axis is perpendicular to the flow of the turbine). Installed capacity of 1.5 MW unit, the diameter of the impeller is 5 m. The block was made to "ON" Sevmash ", and was then towed to the Barents Sea and is set for Kislogubskaya PES . At present (2009) maintained its full-scale tests.
Of a set of blocks of similar design is planned to create a large DOS (including Mezenskaya).
Electricity is expected to send in Western Europe by the ECO "East-West".
In the case of construction of the station annual fuel savings is estimated at 12.6 million tons of standard fuel , which will prevent the emission into the atmosphere of about 19.45 million tons of carbon dioxide.
Garorim Bay Tidal Power Plant Project
9:17 AM
Posted by Energetic
Garorim Bay Tidal Power Plant Project is a planned tidal power plant in Garorim Bay, on the west coast of South Korea. The project is developed by Korea Western Power Company Limited and was in the process of receiving government approval as of November 2008.
Garorim Bay Tidal Power Plant Project is located between Seosan City and Taean County of Chungnam Province, South Korea, at the western seashore of South Korea. The electric power generation capacity of the plant will be 520 megawatt-hours per day (26 MW·h * 20 sets). This is more than twice the capacity of the Rance Power Plant in France, which is the biggest tidal power plant in the world as of 2007.
According to an announcement made by the power company, construction cost was estimated to be 1 trillion Korean won (1 billion US dollars) as of 2005.Environmental impact
Garorim Bay Tidal Power Plant Project is regarded as one of the important tidal flats in South Korea. The Korean government included this bay in the National Wetland Inventory. The Yellow Sea Large Marine Ecosystem (YSLME) Project, managed by the United Nations Development Programme and the Global Environment Facility, also surveyed the ecology of this bay.
According to a survey on fishery resources in 1981, supported by the Korean Ocean Research and Development Institute, this bay is an important spawning ground for many species of fish. The study predicted that the plant's construction would cause critical damage to the bay's ecology.
The bay is one of the most important fish farming sites in Korea, composed of about 2000 fishery households.
Response of local fishermen
On 20 August 2007, the power company tried to hold a Hearing from Residents, an official proceeding required by the Environmental Impact Assessment (EIA). But about 1000 fishermen, demanding cancellation of the entire project, prevented the hearing from being held so the EIA requirement would not be met.
Relation to renewable energy strategy
Garorim Bay Tidal Power Plant Project is now being included in the South Korean government's renewable energy strategy. The Korean government classifies tidal power as renewable, and the Garorim Bay Project is included in the renewable energy plan which the government announced in September 2008.
The Korean Federation for Environmental Movement (Friends of the Earth Korea) has criticized the project, arguing that the power plant is contrary to the purpose of renewable energy, because it would destroy the valuable tidal flats in the area, thus accelerating global warming.
Incheon Tidal Power Plant Project
8:09 AM
Posted by Energetic
The Incheon Tidal Power Plant Project is a large tidal power station currently proposed to be built at the Incheon Bay, South Korea. The facility is expected to top 1,320 MW in generating capacity with the help of 44 water turbines rated at 30 MW each, making this facility one of the largest of it kind in the world. The construction and developments costs are expected to reach ₩3.9 trillion (US$3.4 billion), of which would be entirely covered by private funding. The stations is expected to generate up to 2.41 TWh of energy annually upon its completion in June 2017.
| Incheon Tidal Power Station | |
|---|---|
| Country | |
| Locale | Incheon Bay |
| Status | Proposed |
| Commission date | June 2017 |
| Power station information | |
| Primary fuel | Tide |
| Generation units | 44 × 30MW |
| Power generation information | |
| Installed capacity | 1,320 MW |
| Annual generation | 2.41 TWh |
Severn Barrage Tidal Energy
12:19 AM
Posted by Energetic
A list of ten proposed Severn Barrage Tidal Energy projects was published in July 2008. The feasibility study looked in further detail at the ten schemes and the consultation document published in January 2009 proposed that a short-list of 5 schemes should be the subject of more extensive research in phase two of the study. The 5 schemes are:
- Shoots Barrage (1.05GW scheme located downstream of the new Severn road crossing with an estimated construction cost of £3.2bn)
- Beachley Barrage (625MW scheme located further upstream of the first Severn road bridge with an estimated cost of construction of £2.3bn)
- Bridgwater Bay Lagoon (1.36GW impoundment on the English side of the Estuary with an estimated construction cost of £3.8bn)
- Fleming Lagoon (1.36GW impoundment on the Welsh bank of the Estuary with an estimated construction cost of £4.0bn)
- Cardiff-Weston (Lavernock Point to Brean Down) Barrage (8.46GW scheme, commonly known as the ‘Severn Barrage’, with an estimated cost of construction of £20.9bn).
The Government response to consultation was published in July 2009. This confirmed detailed study in phase 2 would be carried out on the 5 schemes that were recommended in the consultation document. It also announced work to bring forward 3 further schemes that are currently in the very early stages of development.
Power generation potential
The Severn Barrage plans would provide a predictable source of green energy during lifetime of the scheme, 5% of the UK's output from the 10-mile version. This could reduce the cost of meeting UK’s renewable energy targets, and help the UK to meet such targets, including those to tackle climate change. This is because of the few carbon emissions associated with the plan, because unlike conventional power generation, the Severn Barrage plans do not involve the combustion of fossil fuels. A consequence of this plan is that the carbon payback time—the time it takes for saved carbon emissions (those produced by generating the same amount of power in other ways) to outstrip those produced during construction— could be as little as four-and-a-half months, although likely to be around six.
It could continue to operate for around 120 years, compared with 30–40 years for nuclear power plants. An additional benefit would be to improve energy security.
However, although power supply is predictable, peaks in generation from the barrage do not necessarily coincide with peaks in demand. There are two major tidal cycles affecting power output:
- semi-diurnal cycle: the familiar daily rise and fall of the sea with a full cycle every 24 hours and 50 minutes, with two high and low tides, giving maximum power generation opportunities a few hours after each of the two high tides;
- spring-neap cycle: a 29.5 day tidal range cycle with the lowest power days producing about 25% of the power of the highest power days.
Just under eight hours per day of generation time is expected.
Construction costs
Estimated costs for existing plans could be as low as £10bn and as high as £34bn. Recent studies have suggested that the smaller short-listed options could be privately financed, and so in effect the matter of cost and risk becomes a private one between the building consortium and their banks. Schemes of the scale of Cardiff-Weston are likely to require significant Government involvement. If the banks feel that a smaller project is viable and decide to lend the money at an acceptable cost of finance then the projects will go ahead (subject to planning and other approvals). None of this cost would directly fall on the tax-payer but any support mechanism for the tidal power would be likely to fall on consumers. There would though be secondary knock-on costs from the tidal power project that might be met by the tax-payer, such as modifying existing ports, provision of compensatory habitat and dealing with environmental change. However, these would be offset by the positive knock-on effects, such as flood protection - which would have otherwise also cost tax-payer money. Whether the parties actually decided to exchange money for these knock-on effects would be a matter for Government negotiation.
Local impact
Any large-scale barrage would create leisure-friendly water conditions behind it. Flood protection would be provided by the barrage, covering the vulnerable Severn estuary from storm surges from the sea. New road and/or rail transport links could be built across a barrage if demand rises in the future, as outlined below. Any barrage could provide a boost to the local economy — construction industry in the short term, tourism and infrastructure in the long term.
However, shipping would have to navigate locks, and existing estuary industries, including fisheries, would be damaged and jobs lost. All industrial discharges into the River Severn (e.g. from Avonmouth) would have to be reassessed.
Penzhin Tidal Power Plant Project
9:47 AM
Posted by Energetic
The Penzhin Tidal Power Plant Project is a set of proposals for construction of tidal power plant in the Penzhin Bay, which is an upper right arm of Shelikhov Bay in the north-east corner of the Sea of Okhotsk. Because Penzhin Bay has one of the strongest tides, several projects of power station was suggested. One of proposed variants presumes installed capacity 87 GW and annual production 200 TWh of electricity.
Geographically, the dam of the power station would extend through the administrative border of Magadan Oblast and Kamchatka Krai of Russia.
The altitude of tides in Penzhin Bay constitutes 9 metres (30 ft) and reaches 12.9 metres (42 ft) in the case of syzygian tides, that is the highest magnitude for Pacific ocean. As the area of the bay basin is 20,530 km² (7,930 mi²), it corresponds to diurnal discharge of 360−530 km³ (86−130 cu mi). This water rate is 20-30 times higher, than it is for the Amazon River, the biggest river of the Earth. Two projects were developed for tidal power stations. First of them is earliest in time and proposes use of entire basin of the bay. The second one suggests smaller scale plant, which must use northern part of basin with higher tides:
| Variant | Tide altitude, m \ ft | Capacity, GW | Annual production, TW·h | Time of research |
|---|---|---|---|---|
| South site | 11 \ 36 | 87,1 | 190-205 | 1972—1996 |
| North site | 13.4 \ 44 | 21,4 | 50 | 1983—1996 |
Due to the lack of local consumers and power lines, there are suggestions of a discrete work of the station to supply power-consuming productions. One of such regulators, for example, would be the production of liquid hydrogen.
Hydrological potential of the bay
The tides in the Penzhin Bay of the Sea of Okhotsk is highest one for Pacific ocean reaching the height 13.4 metres (44 ft). The tides in Shelikhov Bay is a duirnal type, the area of Penzhin Bay basin is 20 530 km². Hence, the assumption, that the average magnitude of tide is equal to 10 metres (33 ft), gives the diurnal flow of water in the bay equal to 410.6 cubic kilometres (98.5 cu mi) or average discharge 4.75×106 m3•sec-1.
The passing stream has its own potential energy, which in the gravity field of Earth is above zero only in the case of non-zero head of water (HHead) and can be expressed as follows:
, (1)
where E denotes potential anergy; ρsw — density of sea water, equal to 1,027 kg/m³; SBasin — area of basin; HTide — height of the tide and g — gravitational acceleration, set to 9.81 m/sec². The part of expression in brackets denotes terms defining the mass of water passing through the basin daily.
As it can be seen in formula (1), the potential energy becomes zero in the case of zero head of water and in the case of equal heights of head and tide. Regarding this formula as function of head (HHead), it is a parabolic function, which has the maximum at HTide = 2•HHead or at HHead = 5 m. This value of HHead gives two times lower height of tide in the bay and twice smaller average discharge of water — 5 m and 2.38×106 m3•sec-1 (205.3 km³/day), correspondingly.
The substitution of obtained parameters into (1) and dividing it by the day length in seconds gives the average capacity 120 GW. The latter one allows to obtain 1,054 TW•h or 3.79×1018 Joules of energy annually. Depending on the efficiency of conversion of potential energy into electricity, the total quantity of electricity and electric capacity will have somewhat lower values. The assumption, that the efficiency of conversion is equal to 96%, gives an average electric capacity 115 GW and available amount of electricity 1,012 TW•h or 3.64×1018 J per year.
Sihwa Lake Tidal Power Plant
5:49 AM
Posted by Energetic

Sihwa Lake Tidal Power Plant is a large tidal power station currently under construction. Due to be completed in December 2010 and it will operate with a total power output capacity of 254 MW, surpassing the 240 MW Rance Tidal Power Station to become the world's largest tidal power installation.
The tidal barrage makes use of a seawall constructed in 1994 for flood mitigation and agricultural purposes. Ten 25.4 MW submerged bulb turbines are driven in an unpumped flood generation scheme; power is generated on tidal inflows only and the outflow is sluiced away. This slightly unconventional and relatively inefficient approach has been chosen to balance a complex mix of existing land use, water use, conservation, environmental and power generation considerations.
The Sihwa Lake Tidal Power Plant should provide indirect environmental benefits as well as renewable energy generation. After the seawall was built, pollution built up in the newly created Sihwa Lake reservoir, making its water useless for agriculture. In 2004, seawater was reintroduced in the hope of flushing out contamination; future inflows from the tidal barrage are envisaged as a complementary permanent solution.
Cost of the Sihwa Lake Tidal Power Plant project is being met by the South Korean Government and at present totals 313.5 billion won. Mean operating tidal range is 5.6 m (18 ft), with a spring tidal range of 7.8 m (26 ft). The working basin area is 43 km2 (17 sq mi).
| Sihwa Lake Tidal Power Plant | |
|---|---|
| Country | |
| Locale | Sihwa Lake, Gyeonggi Province |
| Status | Under construction |
| Opening date | December 2010 |
| Construction cost | ₩313.5 billion |
| Owner(s) | Korean Water Resource Corporation |
| Power station | |
| Type | Tidal barrage |
| Turbines | 10 × 25.4 MW |
| Installed capacity | 254 MW |
Uldolmok Tidal Power Plant
6:59 AM
Posted by Energetic

Uldolmok Tidal Power Plant is a tidal power station in Uldolmok, Jindo County, South Korea. The plant was commissioned in May 14, 2009 (2009-05-14) by the South Korean government. The plant cost US$10 million and has an installed capacity of 1,000 KW (1 MW), generating 2.4 GWh annually, sufficient to meet the demand of 430 households.
The South Korean government plans to increase this capacity of 1 MW to 90 MW by the end of the year 2013, increasing the demand cover to 46,000 households, while simultaneously working on the 254 MW Sihwa Lake Tidal Power Station. Part of the goal of generating 5,260 GWh through tidal power by 2020.
The Uldolmok Strait experiences tidal water speeds that exceed 6.5 m/s (21.3 ft/s) with the width of the strait being approximately 300 m (980 ft).| Uldolmok Tidal Power Plant | |
|---|---|
| Locale | Uldolmok, Jindo, South Korea |
| Construction began | May 14, 2009 (2009-05-14) |
| Construction cost | US$10 million |
| Dam and spillways | |
| Type of dam | Barrage |
| Length | 3,260 m (10,696 ft) |
| Impounds | Uldolmok Strait |
| Power station | |
| Installed capacity | 1,000 KW |
| Annual generation | 2.4 GWh |
Strangford Lough SeaGen Tidal Stream Power Station
11:04 AM
Posted by Energetic

Strangford Lough SeaGen is the world's first large scale commercial tidal stream generator located in Strangford Lough. It is more powerful than any other tidal stream generator in the world. In 2007 Strangford Lough SeaGen became home to the world's first commercial tidal stream power station. The 1.2 megawatt underwater tidal electricity generator, part of Northern Ireland's Environment and Renewable Energy Fund scheme, takes advantage of the fast tidal flow in the lough which can be up to 4 m/s. Although the generator is powerful enough to power up to a thousand homes, the turbine has a minimal environmental impact, as it is almost entirely submerged, and the rotors turn slowly enough that they pose no danger to wildlife.
The first SeaGen generator was installed in Strangford Narrows between Strangford and Portaferry in Northern Ireland in April 2008 and was connected to the grid in July 2008. It generates 1.2 MW for between 18 and 20 hours a day while the tides are forced in and out of Strangford Lough through the Narrows. Interestingly, Strangford Lough was also the site of the very first known tide mill in the world, the Nendrum Monastery mill where remains dating from 787 have been excavated.
Since June 2008 a tidal energy device called Evopod has been tested in Strangford Lough near the Portaferry Ferry landing. The device is a 1/10 scale prototype and is being monitored by Queens University Belfast. The device is a semi submerged floating tidal turbine and is moored to the seabed via a buoy mounted swivel so that it always maintains optimum heading into the direction of the tidal flow. The scale device is not grid connected and dissipates the small amount of power it generates as heat into the sea.
Technology
SeaGen generator weights 300 tonnes. It consists of twin axial-flow rotors of 16 metres (52 ft) in diameter, each driving a generator through a gearbox like a hydro-electric or wind turbine. These turbines have a patented feature by which the rotor blades can be pitched through 180 degrees allowing them to operate in both flow directions – on ebb and flood tides. The power units of each system are mounted on arm-like extensions either side of a tubular steel monopile some 3 metres (9.8 ft) in diameter and the arms with the power units can be raised above the surface for safe and easy maintenance access. The SeaGen was built at Belfast's Harland and Wolff's shipyards.[9]
Environmental impact
SeaGen has been licensed to operate over a period of 5 years, during which there will be a comprehensive environmental monitoring programme to determine the precise impact on the marine environment.
Kislaya Guba Tidal Power Plant
4:50 AM
Posted by Energetic

The Kislaya Guba Tidal Power Plant is an experimental project in Kislaya Guba, Russia.
The Kislaya Guba Tidal Power is the world's 4th largest tidal power plant with the output capacity of 1.7 MW. Construction on the project began in 1968, but was later suspended for 10 years until December 2004, when funding resumed. The site was originally chosen because the long and deep fjord had a fairly narrow outlet to the sea which could easily be dammed for the project. There are plans for two larger scale projects based on this design near Mezen, on the White Sea and Tugur on the Sea of Okhotsk.| Kislaya Guba Tidal Power Station | |
|---|---|
| Country | |
| Locale | Kislaya Guba |
| Status | Operational |
| Commission date | 1968 |
| Owner(s) | RusHydro |
| Power station information | |
| Primary fuel | Tide |
| Generation units | 1 × 0.2 MW 1 × 1.5 MW |
| Power generation information | |
| Installed capacity | 1.7 MW |
Jiangxia Tidal Power Plant
3:44 AM
Posted by Energetic

The Jiangxia Tidal Power Plant located in Wuyantou, Wenling City, Zhejiang Province, China. It is the third largest tidal power station in the world. Although the proposed design for the facility was 3,000 KW, the current installed capacity is 3,200 KW, generated from one unit of 500 KW, one unit of 600 KW, and three units of 700 KW, totalling the installed capacity to 3,200 KW. Proposals were made to install a sixth 700 KW unit, but this has not yet been installed.[2][3] The facility generates up to 6.5 GWh of power annually.
The Jiangxia Tidal Power Plant feeds the energy demand of small villages at a 20 km (12 mi) distance, through a 35-kV transmission line. The maximum tidal range in the estuary is 8.39 m (27.5 ft).| Jiangxia Tidal Power Plant | |
|---|---|
| Country | |
| Locale | Wuyantou, Wenling, Zhejiang |
| Status | Operational |
| Dam and spillways | |
| Type of dam | Barrage |
| Reservoir | |
| Tidal range | 8.39 m (27.5 ft) |
| Power station | |
| Commission date | April 1980 |
| Type | Tidal barrage |
| Turbines | 1 × 500 KW 1 × 600 KW 3 × 700 KW |
| Installed capacity | 3.2 MW |
| Maximum capacity | 3.9 MW |
| Annual generation | 6,500 MWh |
Annapolis Royal Tidal Power Plant
6:57 AM
Posted by Energetic

The Annapolis Tidal Power Plant is a 20 MW tidal power station located on the Annapolis River immediately upstream from the town of Annapolis Royal, Nova Scotia, Canada. It is the only tidal generating station in North America. The generating station harnesses the tidal difference created by the large tides in the Annapolis Basin, a sub-basin of the Bay of Fundy. Opened in 1984, the Annapolis Royal Generating Station was constructed by Nova Scotia Power Corporation, which was, at the time, a provincial government Crown corporation that was frequently used to socially benefit various areas in the province.
The project has had mixed results. While effectively generating electricity, the blocking of water flow by the dam (to allow the tidal difference to accumulate every six hours) has resulted in increased river bank erosion on both the upstream and downstream ends. The dam is also known as a trap for marine life. Two notable cases occurred in:
- August 2004: a mature Humpback whale (nicknamed Sluice) swam through the open sluice gate at slack tide, ending up trapped for several days in the upper part of the river before eventually finding its way out to the Annapolis Basin.
- Spring 2007: When a body of an immature Humpback whale was discovered near the head of tide in the river at Bridgetown. A post-mortem was inconclusive but suggested the whale had become trapped in the river after following fish through the sluice gates.
| Annapolis Royal Generating Station | |
|---|---|
| Country | Canada |
| Locale | Annapolis Royal, Nova Scotia |
| Status | Operational |
| Commission date | 1984 |
| Owner(s) | Nova Scotia Power |
| Power station information | |
| Primary fuel | Tidal |
| Power generation information | |
| Installed capacity | 20 MW |
| Annual generation | 50 GWh |
Rance Tidal Power Plant
6:27 AM
Posted by Energetic

The Rance Tidal Power Plant is the world's first tidal power station. The facility is located on the estuary of the Rance River, in Brittany, France. Opened on the 26th November 1966, it is currently operated by Électricité de France, and is the largest tidal power station in the world, in terms of installed capacity. With a peak rating of 240 Megawatts, generated by its 24 turbines, it supplies 0.012% of the power demand of France. The annual output is approximately 600 GWh. The barrage is 750 m (2,461 ft) long, from Brebis point in the west to Briantais point in the east. The power plant portion of the dam is 332.5 m (1,091 ft) long. The tidal basin measures 22.5 km2 (9 sq mi).
In spite of the high development cost of the project, the costs have now been recovered, and electricity production costs are lower than that of nuclear power generation (1.8c per kWh, versus 2.5c per kWh for nuclear).
Rance Tidal Power Plant Environmental impact
The barrage has caused progressive silting of the Rance ecosystem. Sand-eels and plaice have disappeared, though sea bass and cuttlefish have returned to the river. By definition, tides still flow in the estuary and the operators, EDF endeavours to adjust their level to minimize the biological impact.
Tourist attraction
The Rance Tidal Power Plant facility attracts approximately 200,000 visitors per year. A canal lock in the west end of the dam permits the passage of 16,000 vessels between the English Channel and the Rance. Departmental highway 168 crosses the dam and allows vehicles to travel between Dinard and Saint-Malo. There is a drawbridge where the road crosses the lock which may be raised to allow larger vessels to pass.
| Rance Tidal Power Plant | |
|---|---|
| Country | |
| Locale | Brittany |
| Status | Operational |
| Construction began | 26 July 1963 |
| Opening date | 26 November 1966 |
| Construction cost | ₣620 million |
| Owner(s) | Électricité de France |
| Dam and spillways | |
| Type of dam | Barrage |
| Length | 700 m (2,300 ft) |
| Reservoir | |
| Tidal range | 8 m (26 ft) |
| Power station | |
| Type | Tidal barrage |
| Turbines | 24 |
| Installed capacity | 240 MW |
| Annual generation | 600 GWh |
Largest Tidal Power Plant
7:02 PM
Posted by Energetic
The following page lists most Largest tidal power plant. Since tidal stream generators are an immature technology, no technology has yet emerged as the clear standard. Although, a large variety of designs are being experimented with, some very close to large scale deployment. Hence, the following page lists stations of different technologies.
Largest Tidal power plant
Operational
The following table lists tidal power stations that are in operation as of August 2010.
| Tidal Power Station | Capacity (MW) | Country | Comm |
|---|---|---|---|
| La Rance Tidal Power Plant | 240 | 1966 | |
| Annapolis Royal Tidal Power Plant | 20 | 1984 | |
| Jiangxia Tidal Power Plant | 3.2 | 1980 | |
| Kislaya Guba Tidal Power Plant | 1.7 | 1968 | |
| Strangford Lough SeaGen | 1.2 | 2008 | |
| Uldolmok | 1.0 | 2009 |
Under construction
The following table lists tidal power stations that are currently under construction as of the date in each cited source.
| Tidal Power Station | Capacity (MW) | Country | Comp |
|---|---|---|---|
| Sihwa Lake | 254 | 2010 |
Proposed
The following table lists tidal power stations that are only at a proposal stage.
| Tidal Power Station | Capacity (MW) | Country |
|---|---|---|
| Penzhin Tidal Power Plant Project | 87,100 | |
| Mesen - Mezenskaya Tidal Power Plant | 12,000-8,000 | |
| Severn Barrage Tidal Energy | 8,640 | |
| Tugurskaya Tidal Power Plant | 3,640 | |
| Dalupiri Blue Energy Project | 2,200 | |
| Incheon Tidal Power Plant Project | 1,320 | |
| Garorim Bay Tidal Power Plant Project | 520 | |
| Gulf of Kutch Project | 50 | |
| Skerries Tidal Farm | 10.5 |
Largest Run of the River Hydroelectric Power Plant
6:58 PM
Posted by Energetic
The following page lists the Largest run of the river hydroelectric power plants. This list includes most power stations that are larger than 100 MW in maximum net capacity, which are currently operational or under construction. Those run of the river hydroelectric power stations that are smaller than 100 MW, and those that are only at a planning/proposal stage may be found in regional lists.
| Station | Country | Capacity (MW) |
|---|---|---|
| Jinping-II Hydroelectric Plant | 4,800 | |
| Chief Joseph Dam | 2,620 | |
| John Day Dam Hydroelectric Power | 2,160 | |
| Beauharnois Hydroelectric Power Plant | 1,903 | |
| The Dalles Hydroelectric Dam | 1,779 | |
| Ghazi-Barotha Hydropower Project | 1,450 | |
| La Grande-1 Hydroelectric Plant | 1,436 | |
| Tianshengqiao-II Hydropower Plant | 1,320 | |
| Jean-Lesage Hydroelectric Plant | 1,145 | |
| Bonneville Lock and Dam | 1,092 | |
| Outardes-3 Hydroelectric Plant | 1,026 | |
| McNary Hydroelectric Dam | 980 | |
| Little Goose Lock and Dam | 932 | |
| Lower Granite Lock and Dam | 932 | |
| Lower Monumental Lock and Dam | 932 | |
| Bersimis 2 Generating Station | 869 | |
| Carillon Generating Station | 753 | |
| Birecik Dam | 672 | |
| Outardes-2 Hydroelectric Plant | 523 | |
| Baglihar Dam-Hydroelectric Power Project | 450 | |
| Gilgel Gibe II Power Station | 420 | |
| Ranganadi Dam | 405 |
Subscribe to:
Comments (Atom)