The Bureya Hydroelectric Dam (Bureyskaya) is a hydroelectric power plant on the Bureya River in the Russian Far East.

Bureya Hydroelectric Dam is a gravity dam with height of 139 metres (456 ft) and crest length of 810 metres (2,660 ft).

The power station has an installed capacity of 2010 MW, the full capacity. Power is generated by utilizing six turbines, each with a capacity of 335 MW. The facility is owned by RusHydro.

Bureya hydroelectric power station was built by Bureyagesstroy. Construction started in 1976, but was halted until 1999. In 1999, RAO UES restarted the project. The dam was completed and the first unit was launched in 2003. The construction of the whole complex was completed in 2009.

The reservoir reached its specified level during the summer-autumn monsoon season of 2009. It was accompanied with first use of spillways during planned tests. Despite the fact that all primary construction works on power station was completed, it will be officially commenced for exploitation by government commission in 2011. Therefore, officially, the complex is still under construction.

Bureya Dam
Official name Bureyskaya
Locale Far East, Russia
Coordinates 50°16′07″N 130°18′54″E / 50.26861°N 130.315° / 50.26861; 130.315
Construction began 1976
Opening date 2009
Owner(s) RusHydro
Dam and spillways
Type of dam Gravity dam
Height 139 m (456 ft)
Length 810 m (2,657 ft)
Impounds Bureya River
Reservoir
Capacity 20.94 km3 (5.02 cu mi)
Surface area 750 km2 (290 sq mi)
Power station
Turbines 6 × 335 MW
Installed capacity 2,010 MW