La Grande-1 hydroelectric plant is a run of the river hydroelectric power plant on the La Grande River that is part of Hydro-Québec's James Bay Project. The station can generate 1,436
MW and was commissioned in 1994–1995. A "
run of the river" generating station, it is one of only two generating stations of the James Bay Project that use a reservoir without any major water-level fluctuations (the Laforge-2 generating station is the other). Thus, the amount of electricity generated by the station depends almost entirely on the water-flow of the river, which is largely controlled by upstream reservoirs and generating stations.
La Grande-1 Generating Station |
Official name | La Grande-1 |
Locale | Quebec, Canada |
Construction began | 1993 |
Opening date | 1995 |
Owner(s) | Hydro-Québec |
Dam and spillways |
Impounds | La Grande River |
Spillway capacity | 16,280 m3/s (574,923 cu ft/s) |
Reservoir |
Creates | (Run-of-river) |
Surface area | 70 km (43 mi) |
Power station |
Type | Yes |
Hydraulic head | 27.5 m (90 ft) |
Turbines | 12 × 114 MW (Fixed-blade propeller-type turbine) |
Installed capacity | 1,436 MW |